How To Add a New Funding Stream to a Contract

After a contract is already in progress you may find the need to complete the contract using a new source of funds (Funding Stream).  This type of change will generally require the following steps; however, feel free to contact your Horizon Support Representative if you need assistance.

NAVIGATION:  ACTIVITIES menu > Contract Master

  1. Open the Work/Service Items tab
  2. Do a Downward Adjustment on the existing Work Item so that the revised work item amount equals the Total Posted and Unposted amounts.  (See: How to Adjust a Work Item)
  3. Add a new work item that will be applied to the new funding stream.
  4. Click the first open box under WORK ITEM and select the work item related to this contract or project.  Press TAB.  You can change the description if you like.
    1. Select the AMP using the browse button and tab
    2. Select the Cost Center using the browse button and tab
    3. Enter the Amount related to this Work Type and tab
  5. Press the Go to Work Item Break Down button on the bottom right of the screen
    1. Select the Work Item using the browse button and tab two times
    2. In the grid, enter 100% and tab to the Funding Stream column
    3. Click on the Funding Stream header button and select the funding source for this work item
    4. Tab once and click the blue "X" two times to close the Funding Stream Assignments screen
  6. You are now finished and can close the Contract Master.

2/2021

NEED MORE HELP?  Submit a ticket to the Help Desk or call (814) 535-7810 or (800) 889-3388